
For last 7 months the kitchen of the mess operated in the Admin Building. The mess brought other forms of mess: flies, occasional dogs and I have spotted a cow once. The mess contractor always complained about the effort required to carry the foot 3 stories up and down. We wanted the mess in the Hostel to be ready ASAP.
In our last Construction Review meeting, the contractor promised to deliver the mess by end of the week. We were earnestly hoping that he will keep his promise. As April was coming to an end, I started querying about the status of the mess. Siddhartha told me it may be delayed by a week. I was a little disappointed. Finally, Siddhartha said he will try to advance the delivery by may be two days. I took his word and announced the mess opening on the 5th May.
The entire team swung into action. On 4th the contractor moved his stuff in to the new kitchen. On 5th May the breakfast was served in the mess. I went to the mess at about 11:30 AM. Some kids were taking breakfast :).
The hostel is partially ready. We have given the target of completing the Hostel by June end.
PS: The foyer of the admin block looks a lot cleaner though a bit bereft of life.
PS: The picture shown above shows mess from the US Navy